Plant Investment Details
FCA would invest $1.6 billion to convert the two plants that comprise the Mack Avenue Engine Complexinto the future assembly site for the next-generation Jeep Grand Cherokee, as well as an all-new three-row full-size Jeep SUV and plug-in hybrid (PHEV) models, adding 3,850 new jobs to support production.
The Company intends to start construction of the new Detroit facility by the end of Q2 2019 with the first three-row vehicles expected to roll off the line by the end of 2020, followed by the all-new Grand Cherokee in the first half of 2021.Also as part of this announcement, the Jefferson North Assembly Plant would receive an investment of $900 million to retool and modernize the facility to build the Dodge Durango and next-generation Jeep Grand Cherokee. FCA expects to create 1,100 new jobs at Jefferson North.
The reborn Mack facility would be the first new assembly plant to be built in the city of Detroit in nearly three decades. In 1991, Jefferson North was the last new assembly plant built in the city. When complete, Mack would join Jefferson North as the only automotive assembly plants to be located completely within the city limits of Detroit.The Pentastar engines – the 3.6-, 3.2- and 3.0-liter – currently built at Mack I would be relocated to the Dundee Engine Plant as part of a $119 million investment. Pentastar production at Mack I would end by Q3 2019. Mack II has been idle since it ceased production of the 3.7-liter V-6 in September 2012.FCA also confirms the investment at Warren Truck to retool for production of the all-new Jeep Wagoneer and Grand Wagoneer, announced in 2017, along with their electrified counterparts, would increase to $1.5 billion. Production is expected to launch in early 2021. In addition to the new Jeep models, the plant would continue building the Ram 1500 Classic, which is being extended to meet market demand. It is expected that 1,400 new jobs would be added. As a result of this investment announcement, production of the all-new Ram Heavy Duty will continue at its current location in Saltillo, Mexico.To support the additional production, the Company’s Warren Stamping (Warren, Michigan) and Sterling Stamping (Sterling Heights, Michigan) plants would receive investments of $245 million and $160 million, respectively, with Sterling Stamping expected to add more than 80 new jobs.This investment is part of the Company's capital spending plan presented in June 2018.
Realignment of FCA U.S. Manufacturing Operations
Over the past two years, FCA has realigned production at four plants in Illinois, Ohio and Michigan to increase capacity for the Jeep Cherokee, Jeep Wrangler and Ram 1500 light-duty truck, and created additional manufacturing capacity for the Jeep Gladiator in Ohio.The investments included:
- $350 million in the Belvidere Assembly Plant (Illinois) to produce the Jeep Cherokee, which moved from Toledo, Ohio, in 2017. More than 300 new jobs were added to support production, which launched in June 2017.
- $700 million in the Toledo Assembly Complex (Ohio) to retool the North plant to produce the next-generation Jeep Wrangler. Approximately 700 new jobs were added to support production, which began in December 2017.
- $1.48 billion in the Sterling Heights Assembly Plant (Michigan) to build the next-generation Ram 1500 truck, adding more than 700 new jobs. Production of the new truck began in March 2018. Production of the Ram 1500 Classic continues at Warren Truck (Michigan).
- $273 million in the south plant of the Toledo Assembly Complex to prepare the facility to produce the all-new Jeep Gladiator. The new truck is scheduled to launch in the first half of 2019.
In total, FCA has committed to invest nearly $14.5 billion in its U.S. manufacturing operations, creating nearly 30,000 new jobs since June 2009.
— Press release courtesy of FCA